The Madras High Court on Friday issued notice to the Tamil Nadu government and other authorities on a public interest litigation (PIL) challenging the decision to discontinue the proposed Parandur Greenfield Airport Project. The petitioner has questioned the legality of the decision and sought its reconsideration based on technical assessments and official records.
A Division Bench comprising Chief Justice S A Dharmadhikari and Justice G Arul Murugan directed the Tamil Nadu Industrial Development Corporation Limited (TIDCO), the Union Ministry of Civil Aviation and the Airports Authority of India (AAI) to respond to the petition. The matter will be heard again after four weeks.
The PIL was filed by G Gouthaman, a software consultant and book publisher, who challenged the state government’s August 24, 2026 announcement discontinuing the airport project. He argued that the decision and subsequent administrative orders violated Article 14 of the Constitution.
Petitioner Seeks Reconsideration of Airport Project
Gouthaman has requested the High Court to direct the competent state authorities to review the decision through a reasoned process, taking into account relevant government records and updated expert assessments, including inputs from the AAI.
He has also sought an interim stay on the implementation of the August 24 announcement made by Chief Minister C Joseph Vijay under Rule 110 of the Tamil Nadu Legislative Assembly Rules, along with all consequential executive and administrative orders cancelling the project.
The petition further seeks production of the records relied upon by the government before abandoning the airport proposal. These include internal administrative files, communications between government departments, hydrogeological studies, technical feasibility assessments and financial records.
Earlier Government Approval and Site Selection
According to the petition, the Tamil Nadu government had issued a government order on October 31, 2023, granting administrative sanction for acquiring privately owned patta lands and transferring government lands across Parandur A and 19 other villages in the Kancheepuram and Sriperumbudur taluks of Kancheepuram district to TIDCO.
The order recorded that Parandur had been selected after feasibility assessments conducted by the AAI and TIDCO, which examined several potential locations.
Among the factors favouring Parandur were its proximity to the Chennai-Bengaluru Expressway, comparatively lower estimated population displacement, fewer operational and airspace constraints, reduced land acquisition costs and the possibility of future expansion.
The government had also established a High-Level Committee headed by a retired IAS officer, with experts from IIT Madras and Anna University, to undertake broader hydrological assessments.
The committee was tasked with ensuring that additional water storage capacity created as part of the project would exceed any existing capacity affected by the proposed development.
Sudden Discontinuation Questioned
Despite these earlier administrative approvals and technical assessments, Gouthaman alleged that the state government abruptly decided to abandon the project.
The petitioner has sought judicial scrutiny of the material underlying that decision and requested that the authorities reconsider the proposal after examining updated expert inputs.
The High Court has issued notice to the concerned authorities and scheduled the matter for further hearing after four weeks.